What is a Composite Crew Rate?
Composite crew rates are a common practice for cost estimating. If you are using cost estimating software, you do not need to determine a crew composite rate; the software does it for you. But you still need to set up your crew(s) for your construction activities. Setting up the correct crews for your construction activities, allocating the proper construction equipment and tools, and choosing the correct production rate is the core of cost estimating. Before we begin establishing the composite crew unit rate we need to establish the following:
Labour unit rates for each trade we will be using in the cost estimate. If you are a cost estimator for a construction company, the labour rates you will use are the ones in the labour agreement. If on the contrary, you are a cost estimator working for other than a construction company (engineering, architectural, project owners, etc.) then you will wonder how and where to find such information. Check the category “Resources” for places where you can go to get labour rate information.
Determine the activity list. To do this, you will break down the scope of work into construction activities.
Determine the crew(s) you will use in your cost estimate for each activity.
Determine the OT (overtime) and shift premium based on the construction schedule. This is an adjustment that is most likely done once the cost estimate is complete and a construction schedule is developed.
Living out allowance. If the project requires hiring trade persons who are not local, a living out allowance should be added to the cost estimate. It can be added to the composite crew rate or as an overhead. I always choose to add this cost to the overhead. The living out allowance is based on specific skill levels and not necessarily on a crew. For example, we consider that all trades up to a certain skill level will be out of town. Everybody else will be local.
With all these steps completed, we can start developing the composite crew rates. I keep a database of composite crew rates for activities. Anytime I start a new cost estimate; I refer to this database. I cannot emphasize the importance of the various databases enough that a cost estimator should keep. As important as the actual data in the database are the qualifiers and notes. Therefore, a baseline should be defined for each database.
A crew is made up of only direct labour (and direct equipment, if applicable). Each cost estimate should have its definition of what constitutes direct labour. According to the Business Dictionary, direct labour is “Employees or workers who are directly involved in the production of goods or services.
Direct labour costs are assignable to a specific product, cost center, or work order.” Most construction companies consider field personnel with a rating of the superintendent and higher as part of the overhead costs.
In all my cost estimates as well, all personnel that is not directly involved in construction activity is part of the overhead. Note that equipment operators are part of the crew. If you are using an all-inclusive construction equipment rate in your cost estimate, the equipment operators should not be included in the crew.
For an illustration of how to determine a composite crew rate, I am using a cast-in-place slab on grade textured finish activity. The formwork would be included in other activities. The individual labour rates are for illustration only. Specific labour rates depend on the location of the project, labour relations, and compensation structure specific to the individual construction company.
The workday is 8 hours, Monday to Friday, for a total of 40 hours per week.
Concrete Placing Crew – Slab on Grade, Textured Finish
Description | Qty | Rate/Hr | Total Cost |
Foreman | 0.5 | 49.00 | $24.50 |
Labourers, skilled | 2 | $32.00 | $64.00 |
Cement finishers | 4 | $44.00 | $176.00 |
Total composite crew rate | $40.69 |
The above crew composite rate is based on 70% productivity.
Each crew member spends time on material receiving and handling, site movement, breaks and clean-up. Therefore, we should assume that the rate of $40.69/hr represents 70% productivity.
The typical average productivity for a concrete placing crew is 70%, based on industry cost data.
This average does not take into consideration abnormal variations. The abnormal variations are further accounted for by using the average productivity factor determined specifically for each project. See the “How do You Estimate Labour Productivity” article on this site for details on how it is done.
Let’s assume we evaluated the project we are doing the cost estimate for and the productivity factor is 60%. This means that a loss of 10% should be accounted for. The revised crew composite rate becomes $40.69 x 110% = $44.76/hr.
Once we determined the base composite crew rate in the same fashion, we can further account for any additional costs: overtime, shift premium, etc.
Do not forget to update your database with new activities, crews and crew composite rates.
Did you find this article useful? Please leave your comments and feedback in the comments section.
Do you have a suggestion for a post topic? Do you have any questions? Please comment on this article, or contact me directly: [email protected]. I read and respond to all comments and emails.
Would you like to write for this blog as a guest writer? Please contact me and let me know the topic you would like to write about.
Do you know anyone who would benefit from subscribing to this blog? Please share this post.
Want to know what is coming up on this site? Check the publishing schedule below and the “Coming Soon” page. There are awesome things I am working on!